A pile splice joins two segments of a driven pile, using either a weld (typical for H beams), grout or mechanical means (typical for precast concrete piles). Pile splices enable the use of shorter segments, which allows for driving piles in low-headroom situations such as under bridges or inside buildings.〔("Concrete Pile Splices" ), ''PileBuck International, Inc.''() Retrieved on 7 December 2012.〕 Reducing length of pile segments to under ~65 feet long also means the trailers that haul them to job sites can stay within state length limits.〔("Size & Weight Limits" ), ''America's Independent Truckers' Association, Inc.'' Retrieved on 7 December 2012.〕 ==References== * * * * 抄文引用元・出典: フリー百科事典『 ウィキペディア(Wikipedia)』 ■ウィキペディアで「Pile splice」の詳細全文を読む スポンサード リンク
|